CMAL is pleased to provide an update on the now-vacant CMAL building at Uig. All necessary demolition consents have been granted, and the demolition contractor, Anderson Civil Engineering Limited, has now been appointed. Works commenced on Monday, 9 March, and are expected to be completed by the end of April.

The current timeline for the project is as follows:

  • February 2026: Demolition contract awarded
  • 9 March 2026: Demolition works commence
  • Late April 2026: Demolition works are planned to be complete

If you require further details or have any questions about the demolition project at Uig, please feel free to contact us at uigsite@cmassets.co.uk.