Below are questions/issues raised during public communication meetings in relation to refurbishment works at Wemyss Bay on Tuesday 15th September 2015. Wemyss Bay Project Q and A September 15, Click t
How long will the works take and are you confident that you will meet this revised timetable? What contingency have you built in? The works are programmed to last a total of 24 weeks which will includ