Since the public engagement events in November 2024, we’ve made significant progress on the Tiree Terminal Works Project.

We have successfully completed the detailed design phase for the new terminal building, marshalling area, and car park. This project has been developed in collaboration with our design partners, Graham + Sibbald, and the operator, CalMac. Our final design prioritises both operational efficiency and community needs.

We have just started the tender period to find a suitable contractor for the construction works. Our project team has also worked to secure the required statutory approvals, ensuring that all necessary consents are in place before construction begins.

Key project milestones

  • Project tender issued: Q3 2025
  • Contract awarded: Q4 2025
  • Construction starts: Q1–Q2 2026, subject to funding approval
  • Construction duration: Approximately 12 months

Minimising disruption

We understand the importance of maintaining reliable ferry services and access during the construction phase of these improvement works. Our plans require the chosen contractor to:

  • Keep CalMac ferry timetables operating as normal.
  • Ensure continuous access to all properties and businesses.
  • Provide a temporary terminal building and welfare facilities throughout the construction process.

Questions and answers

We are currently gathering the questions related to this project and will share the finalised Q&A document on our project page in due course.

Contact us

For more information, please visit cmassets.co.uk/tiree-terminal or contact our project team at tiree.terminal@cmassets.co.uk.


Categories: Featured, News, Piers and Harbours, Projects, Tiree Terminal Works
Tags: