Operation to remove sunken barge from Kennacraig Harbour successfully completed
17 June 2010

Work is being undertaken at Kennacraig to remove the sunken barge from near the ferry berth. The five week project will get underway at the start of May 2010, and is vital to allow the new MV Finlaggan ferry currently being built to berth at the harbour in future.
Marine contractors Herbosch-Kiere will be using a large working barge, Waasland, to excavate and remove the old Thames barge which sank in the 1970’s. The project will be managed by consultant engineers Halcrow.
The work will be carried out during the day using an 85 tonne excavator and a 325 tonne crane. There will be no disruption to ferry services.
17 June 2010
22 April 2010
15 April 2010
24 February 2010