Kennacraig Terminal Upgrade Phase - Progress - April 2011
15 April 2011
Construction of the berthing dolphin at Kennacraig has progressed well in the last month. Graham Construction have now completed all the concreting works to the main structure and following a period of curing for the concrete, they will start attaching the fenders, bollards, copes, ladders and lights.