Date of issue: Thursday 5th July 2012
Ref: HP/955/198 - NTM 36/12
Status: Complete

Mariners are advised that CMAL have appointed Jack Tighe Ltd to undertake painting of the linkspan at Castlebay Ferry Terminal, Barra.

The works will commence on Thursday 5th July 2012 and are programmed to last one week.

Works consist of painting the underside of the linkspan and are being undertaken predominantly from a pontoon which, dependent upon tidal conditions may be concealed from view.

All works will be undertaken between arrivals of the scheduled ferry services causing no disruption to the service. 

All vessels navigating in the vicinity of Castlebay Ferry Terminal must therefore do so with caution and regulate their speed to minimise the effects of wash accordingly.

Further details can be obtained using the contact details below.

David McHardie
Harbour Master
Caledonian Maritime Assets Limited

david.mchardie@cmassets.co.uk / 01475 749 920